Signs of The Times
Forgotten Links: Focus on Existing Projects, Not "River
Garland" by Som Pal
http://timesofindia.indiatimes.com/articleshow/868111.cms
Forgotten
Links: Focus on Existing Projects, Not 'River Garland'
SOM
PAL

[ THURSDAY,
SEPTEMBER 30, 2004 12:00:00 AM ]
The 'Garland of Hope' (Aug 14) by
Suresh Prabhu, chairman of the task force on the river linking project,
contains
the oft-repeated data on rainfall, utilisable and already harnessed
water
resources. The core issues needing straight answers seem to have
escaped his
attention, some of which have since been addressed by Dunu Roy in his
'Garland
of Hype' (Aug 27). The present write-up is a humble attempt to fill the
gap.
The idea of linking the rivers was first mooted by K L Rao
during 1970s, and later by Capt M N Dastur. In 1982, the Union
government set up
the National Water Development Agency (NWDA) to study all the aspects
and
prepare feasibility reports. The NWDA has identified two components —
the
Himalayan comprising 16 northern rivers and the Peninsular having 14
southern
rivers. The estimate of investment needed is Rs 5,60,000 crore and the
irrigation potential as 25 million hectares.
The assumption that
there is surplus water available for transfer to other basins is not
correct.
Most of the river basins of India are deficit ones. It may be argued
that the
flood waters during the monsoon can be transferred to deficit areas.
But most of
the existing dam reservoirs seldom get filled to cater to the given
requirements
of irrigation and power generation. The flooded rivers also carry a
huge load of
silt, which is likely to choke the channels. De-silting operations
would involve
disproportionate recurring expenditure. Usually there is no demand for
irrigation in the rainy season, and the quantum, and the period when
overflows
would be available, is uncertain.
Brahmaputra is the only river with
surplus water, which can be brought to the eastern states either
through
Bangladesh or the narrow strip between Bangladesh and Nepal borders.
Both,
however, are fraught with almost insurmountable problems. The other
route lies
in the area categorised as 'danger zone 5' for its high level of
seismic
vulnerability. Advancements in the science of civil engineering perhaps
can take
care of safety of dams against seismic shocks. But insulating a long
canal from
such hazards, however, should be a very high cost affair, besides not
being
foolproof. Even a hairline crack in the bottom or the bank can cause
catastrophic floods.
The Himalayan link canal proposed by Capt Dastur
was considered unfeasible for two reasons. First, the investment
required was
put at Rs 12 lakh crore, which was considered grossly disproportionate.
Secondly, the extremely fragile lower Himalayan terrain frequently
visited by
earthquakes and landslides was not suitable for such a lengthy
structure. Taking
the Ganga water to the southern plateau involved steep lifts up to
several
hundred feet at some places. Technical feasibility apart, the immense
investment
and energy needed would not be commensurate with the potential
benefit.
No less important are the political and legal problems. The
way various states have been quarrelling with each other over water,
flouting
not only the tribunal awards but also the apex court orders, poses a
serious
question mark on the feasibility of the project.
The moot point is
whether there could be a viable approach to solving the water problem.
The Tenth
Plan document has presented a scenario. According to the Plan, there
are 383
ongoing major and medium projects awaiting completion, 111 of which are
pending
since pre-fifth Plan period i.e. more than 26 years. All these can be
completed
within five to eight years, yielding an additional potential of about
14 million
hectares at a cost of Rs 77,000 crore as estimated by the plan task
force, now
raised to Rs 100,000 crore. The second component listed in the Plan is
development of minor irrigation, mostly in the eastern and north
eastern
regions. The total potential assessed is 24.5 million hectares with a
total
investment of Rs 54,000 crore, of which the government is expected to
provide
only Rs 13,500 crore, the balance coming from beneficiary farmers and
institutional loans. The success of such a scheme has clearly been
demonstrated
in Assam, where only 33,000 tubewells, of the planned 100,000, have
helped the
perennially foodgrain deficit state become surplus one within two to
three
years. The cost per hectare is only Rs 20,000 and gestation period
almost nil,
against a cost of Rs 100,000 and 12 years' gestation in case of major
and medium
projects. The annual rainfall in the region, ranging from 1,200 mm to
5,000 mm,
is enough to keep the groundwater regularly recharged. Most of the
tubewells
being shallow, the cost of installation and power consumption would be
low. The
third equally beneficial scheme mentioned in the Plan is the
groundwater
recharge master plan prepared by the Central Ground Water Board needing
Rs
24,500 crore to trap 36 billion cubic metres of water annually. The
Plan,
however, has allocated only paltry sums for this exercise.
There is a
readily available alternative which can create about 50 million
hectares of
irrigation potential in five to eight years with an investment of Rs
1,38,000
crore. Legal, environmental, resettlement and distributional issues
either do
not arise or have been settled. On the other hand, there is a
far-fetched plan
requiring Rs 5,60,000 crore expected to yield only 25 million hectare
irrigation
and fraught with so many insurmountable problems. The choice seems
clear.
(The author is a former
minister of state for agriculture and water resources.)
Warning: Unknown: Your script possibly relies on a session side-effect which existed until PHP 4.2.3. Please be advised that the session extension does not consider global variables as a source of data, unless register_globals is enabled. You can disable this functionality and this warning by setting session.bug_compat_42 or session.bug_compat_warn to off, respectively. in Unknown on line 0